摘要
以多宝山铜矿为例,利用矿山已有数据建立矿山三维模型,进行露天境界优化、采场设计、编制采剥计划。建立了露天生产可视化管理系统,能够有效地指导采掘计划的编制和生产管理工作,并以工程实际应用情况分析了建模结果的可行性和科学性,在数字矿山架构的基础上,探讨了露天矿的可视化开采方案,为数字矿山的建设提供了有效的集成系统。
Took Duobaoshan Copper Mine as a example, 3d mine model was established by using mine existing data, open pit limit optimization, stope design and stripping plan compilation were done, open pit mining visual management system was built, which would effectively direct the compilation of mining plan and production management, feasibility and scientific of modeling results were analyzed based on engineering practical application. On the basis of digital mine structure, visual solve scheme of open-pit mine was discussed, provided effective integrated system for construction of digital mine.
出处
《现代矿业》
CAS
2012年第10期11-14,共4页
Modern Mining
基金
福州大学科技发展基金(编号:2009-XQ-34)