摘要
为解决陆丰13-2导管架隔水导管打桩作业防斜及打桩过程控制问题,对该油田9口井槽隔水导管打桩作业从打桩设备的选用到打桩作业顺序优化设计进行分析研究,同时将隔水导管打桩优化设计结果与现场所收集的数据进行对比,对打桩作业进行全程监控和指导。研究表明,开展隔水导管打桩优化设计研究能够很好地指导现场打桩作业。
Lufeng 13-2 jacket platform stand in deep water.In order to make the piling work smoothly,the conductor piling operations was analyzed for the nine well slots in this field.Considering the selection of equipment and assignments sequence optimization design of piling work,and comparing of our drilling conductor piling optimization design with the date from well site was made,the process of the piling operations were also monitored and guided.It showed that optimization design of drilling conductor piling guides the site work well for the Lufeng 13-2 oilfield.
出处
《船海工程》
2012年第5期170-172,共3页
Ship & Ocean Engineering