基于模糊动态规划法的关键链缓冲确定新方法 被引量:6

A New Method to Identify Critical Chain Buffer Based on the Fuzzy Dynamic Programming
下载PDF
导出
摘要 针对当前关键链项目管理技术缓冲确定过于主观,评价因素中定性指标无法定量表示的现状,将模糊优选理论与动态规划最优化原理相结合,提出了基于模糊动态规划法的关键链缓冲确定新方法。该方法在通过专家评议法得出项目中的富余工期后,结合语气算子与定量标度之间的对应关系将定性指标定量化,综合考虑项目工期、质量、成本指标之间矛盾统一的关系,对项目各道工序的工期进行压缩,并根据模糊决策集优越性二元对比矩阵及决策序列相对优属度总和最大法来确定关键链缓冲,并在实例分析中用软件模拟,验证了该方法的有效性。 Because critical chain project management technology to identify buffer is too subjective and qualitative factors cannot be quantified, combining the theory of fuzzy optimization with dynamic programming optimization theory, a new method to determine the sum of the maximum buffer size according to the fuzzy decision is proposed. After the spare time is achieved by the expert, qualitative indexes are quantified considering mooting operator and quantitative scaling relationship. Considering the contradictory relationship among project schedule, quality and cost index, procedures duration of project are compressed. Based on fuzzy decision set of superiority of the two element contrast matrix and decision sequence relative membership degree method, sum of the maximum sequence of decisions relative membership degree method is used to determine the buffer size. The method is verified by examples of simulation.
出处 《工程管理学报》 2012年第5期74-78,共5页 Journal of Engineering Management
关键词 关键链项目管理方法 缓冲机制 模糊动态规划法 critical chain project management buffer Fuzzy dynamic programming method
  • 相关文献

参考文献6

二级参考文献25

  • 1李喆,欧阳斌,冯艺.大型水利工程关键链进度计划方法研究[J].水利水电技术,2005,36(11):70-73. 被引量:7
  • 2杨耀红,汪应洛,王能民.工程项目工期成本质量模糊均衡优化研究[J].系统工程理论与实践,2006,26(7):112-117. 被引量:55
  • 3潘开灵 尹柳营.用制约因素理论指导企业技术进步[J].中国学术期刊文摘,1997,3(4).
  • 4McKIM R, HEGAZY T, ATTALLA M. Project performance control in reconstruction projects[J].Journal of Construction Engineering and Management,2000,126(2):137-141.
  • 5RWELAMILA P D, HALL K A. Total systems intervention: an integrated approach to time, cost and quality management[J].Construction Management and Economics,1995,13(3): 235-241.
  • 6RAMON J, CRISTOBAL S. Time, cost, and quality in a road buil-ding project[J].Journal of Construction Engineering and Management,2009,135(11):1271-1274.
  • 7EI-RAYES K, KANDIL A. Time-cost-quality trade-off analysis for highway construction[J].Journal of Construction Engineering and Management,2005,131(4):477-486.
  • 8Goldratt E M. What is this thing called the theory of constraints? [M]. NY: North River Press, 1990.
  • 9Goldratt E M, Cox J. The Goal [M]. Aldershot England: Gower, 1993.
  • 10Goldratt E M. It's Not Luck [M]. Aldershot England: Gower, 1994.

共引文献53

同被引文献49

引证文献6

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部