摘要
针对某1 000 MW核电厂倒送电期间负荷不足,母差、辅变差动、线路保护无法校验的问题,进行了深入分析,提出了多种解决方案,并对各个方案的优缺点进行了比较。
Many problems occurred in a 1000MW nuclear power plant in the period of the reverse power supply,such as insufficient load,busbar differential protection,auxiliary transformer differential protection and failure to check line protection.This paper makes in-depth analysis of all these problems,proposes various solutions and compares the pros and cons of these schemes. Abstract: reverse power supply;protection;on-load test
出处
《华东电力》
北大核心
2012年第10期1858-1859,共2页
East China Electric Power
关键词
倒送电
保护
带负荷检验
reverse power supply
protection
on-load test