摘要
采用沉井施工地下筒体结构法,从降低地下水位到旋流井封底施工共经历了四个阶段,最终成功地完成了族流井施工的全过程。
By using open caisson and the hollow underground column structure method, the construction experienced four stages from water level reduction to sinkwell back over, and accomplished the whole process of open caisson construction at last.
出处
《包钢科技》
2000年第3期70-77,共8页
Science & Technology of Baotou Steel