摘要
某电厂引水钢管穿过长江大堤,采用顶管法施工,循环水泵房采用沉井法施工。主要介绍电厂引水工程的防渗设计。
The diversion steel pipe of a power plant through the Yangtze River levee, use the pipe jacking construction method, circulating pump house caisson method construction, this article mainly introduces the design of seepage control in power plant water diversion project.
出处
《水利科技与经济》
2012年第11期22-24,共3页
Water Conservancy Science and Technology and Economy
关键词
电厂
钢管
泵房
灌浆
防渗墙
power plant
steel tube
pump house
grouting
cutoff wall