摘要
介绍了瀑布沟水电站2号电抗器B相油位计更换的原因,详细论述了导油流程方案①和②的优缺点及方案的比选,并介绍了新的顶油枕方法。通过导油流程优化和顶油枕方法优化,使油位计更换工期缩短,工程费用减少。
The reasons of the replacement of B-phase oil gauge of No. 2 reactor in Pubugou Hydropower Station are intro- duced. The advantages, disadvantages and the comparison of the oil guide process scheme (1) and (2) are described in detail. A new method for conservator jacking is presented. The period of oil gauge replacement is shortened and the cost of the project is decreased by the optimization of oil guide process and conservator jacking method.
出处
《水电与新能源》
2012年第6期43-45,共3页
Hydropower and New Energy
关键词
电抗器油位计
流程优化
瀑布沟水电站
oil gauge of reactor
process optimization
Pubugou Hydropower Station