摘要 厦漳跨海大桥北汊北引桥,为跨径50m的混凝土等截面连续箱梁。其中17跨位于岸滩上,9跨位于海上,墩身高度25.331~48.194m。采用下行式移动模架施工,模架主体结构在地面拼装后,通过墩顶提升系统整体提升到预定位置,在提升过程中安装模架支撑系统。该整体提升技术是解决高墩身大型构件高空拼装投入大、风险高、成本高等问题的有效方法。 North approach bridge of Xiazhang Sea - crossing Bridge was made by contant section continuous box beam of 50m span. The 17 cross is located in the beach, 9 cross is located offshore with pier height of 25. 331 - 48. 194m. Using downward moving formwork, mold structure was lifted to a predetermined position after assembled on the ground by pier top lifting system. At the process of lifting formwork supporting system was installed. The whole lifting technology is an effective method to solve the problems of high pier large component as- sembling such as high input, high risk and high cost.
作者 陈山亭
出处 《福建建设科技》 2012年第6期64-67,共4页 Fujian Construction Science & Technology
关键词 高墩 移动模架 整体提升 施工技术 桥梁施工 High pier whole lifting of Mobile formwork Construction technology Bridge construction
  • 相关文献

参考文献4

  • 1中铁大桥局集团公司.MBECl010-2010中铁大桥局集团企业标准[S].
  • 2上海同新机电控制技术有限公司.移动模架液压同步提升施工技术方案,2010.
  • 3杨文渊 徐.桥梁施工工程师手册[M].北京:人民交通出版社,1995..
  • 4中交第一公路工程局有限公司JTG/TFS0-2011公路桥涵施工技术规范[S].北京:人民交通出版社,2011.

共引文献30

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部