摘要
分析了火力发电机组取消旁路烟道的技术可行性和安全性,讨论了旁路烟道取消后给机组及脱硫系统带来的一系列技术问题,结合现有无旁路脱硫系统的运行实践,对取消旁路后出现的问题,从设备改造、运行调整等方面提出了应对措施。
The paper analyzes technical feasibility and safety of removing bypass flue from thermal generator sets and it discusses technical problems brought to units and desulphurization system due to the removal of bypass flue. In combination with practical operation of current non-bypass desulphurization system, the paper proposes countermeasure against problems due to removal of bypass in terms of equipment transformation, operation adjustment and so forth.
出处
《浙江电力》
2012年第11期69-72,共4页
Zhejiang Electric Power
关键词
发电厂
脱硫
烟道旁路
取消
power plant
desulphurization
bypass flue
removal