三峡二期工程1&2B标合同商务管理回顾

Review of commercial management for TGP Stage Ⅱ works 1&2B contracts
下载PDF
导出
摘要 三峡二期工程 1&2B标的合同商务问题主要由于业主提供设备滞后和存在缺陷等条件变化 ,引起合同条款中存在模糊、歧义和设计变更等情况。 1&2B标规模大、施工强度高、技术复杂 ,事先难以预料的风险因素多 ,合同商务问题的处理格外困难。由于参建各方严格遵守公平诚信的原则 ,以合同为依据 ,互相协商 ,保障和促进了质量、进度目标的实现。监理工程师在业主单位授权的范围内或在其同意的情况下 ,指示承包者对工程作出某种变更时 ,根据合同条款规定 ,对其进行估价 ,并与业主、承包商协商价格。 1&2B标在实施过程中出现了为数不少的索赔 ,监理工程师在处理索赔时 。 The commercial issues about TGP Stage Ⅱ works 1&2B contracts mainly arose from such facts as that the owner did not provide the relevant equipments on time, and some equipments had defects. There are indistinct meanings in some provisions of the contracts, in addition to design changes. Settlement of the commercial issues about 1&2B contracts is very difficult, because of large engineering scale, high construction intensity, complex technology, and a lot of unexpected risk factors. Aims of good engineering quality and quick construction progress of the contract works, however, have been achieved, as a result of that the principles of fairness, consultation, taking contract as basis, are complied with by parties concerned. Under owners authorization, the supervisory engineer may instruct the contractor to make some changes in contract works, and corresponding work quantities and prices are defined both by contract and through consultation. In settling the issues about claim indemnity in carrying out 1&2B contract works, the interests of both owner and contractors were fairly and reasonably considered by supervisory engineers.
作者 文军
出处 《人民长江》 北大核心 2000年第7期4-5,9,共3页 Yangtze River
关键词 施工合同 商务管理 设计变更 三峡二期工程 construction contract commercial management design alteration claims for project alteration TGP Stage Ⅱ works
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部