呼和浩特抽水蓄能电站引水系统开挖研究 被引量:3

Study on excavation of water diversion system of Hohhot Pumped Storage Power Station
下载PDF
导出
摘要 结合实际工程,介绍了呼和浩特抽水蓄能电站引水系统开挖采用的ALIMAK爬罐结合反井钻斜井导洞开挖的施工方案。其中,不但归纳了其施工方法的优点并简单地介绍了其施工的过程,而且介绍了其现场施工精度的控制措施,最后列出了现场斜井贯通的测量成果。本研究对类似工程斜井开挖有一定的参考价值。 Based on the actual project, the construction technology of excavating the pilot heading for the inclined shaft by rai- sing-boring machine combined with ALIMAK climber during the excavation of the water diversion system of Hohhot Pumped Stor- age Power Station is introduced herein; in which, not only the merits of the construction method are summarized along with the description on its construction process, but the measures for the control of the in situ construction precision are also presented, furthermore, the measurement result of the breakthrough of the inclined shaft is finally listed as well. This study has a certain ref- erence value for the excavation of inclined shaft of the similar project.
出处 《水利水电技术》 CSCD 北大核心 2012年第11期58-60,65,共4页 Water Resources and Hydropower Engineering
关键词 引水系统 斜井 导洞 开挖技术 精度控制 呼和浩特抽水蓄能电站 water diversion system inclined shaft pilot heading excavation technology precision control Hohhot Pumped Storage Power Station
  • 相关文献

参考文献5

共引文献34

同被引文献7

引证文献3

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部