摘要
针对司家营铁矿开拓系统采用3条立井和井下溜破系统联合布置的特点,结合施工现状,明确了各主井的施工任务,优化了溜破系统的施工顺序,确定了各主井的装备时间和顺序,有效地缩短了矿山建设工期,为司家营铁矿顺利建设奠定了基础。
in response to the feature of combined arrangement of 3 shafts and underground ore pass fragmenting system introduced in Sijiaying Iron Mine and the construction conditions, .the paper describes construction tasks for the major shafts, optimizes construction sequence of ore pass fragmenting, identifies equipping time and order for the major shafts, effectively shortening the construction period and laying a foundation for smoothly con strueting Sijiaying Iron Mine.
出处
《化工矿物与加工》
CAS
北大核心
2012年第12期38-41,共4页
Industrial Minerals & Processing
关键词
溜破系统
联合布置
施工顺序
永久装备
ore pass fragmenting
combined arrangement~ con- struction sequence permanent equipment