摘要 针对兰花集团莒山煤矿煤柱综采放顶煤回收工作面回采过程中频繁过空的实际,依据ZF302工作面过旧巷开采实践,对煤柱综采放顶煤回收工作面过旧巷前后的顶板状况及矿压显现进行了描述,着重论述了煤柱综放回收工作面过旧巷回采过程中所采用施工工艺和对顶板、设备、通风、旧物回收等方面的技术管理,并总结出了许多宝贵经验。 Aiming at the reality of frequently passing empty areas in coal pillar fully mechanized top coal recovery working face in coal extraction process, according to mining practice through old roadway in ZF302 working face, described the roof condition and mining pressure appearance before and after passing though the old roadway in coal pillar fully mechanized top coal recovery working face, focused on the construction technology applied and technical management of roof, equipments, ventilation, old mate- rial recycling, etc., and summed up a lot of valuable experience.
作者 崔文峰
出处 《能源与节能》 2012年第12期3-4,15,共3页 Energy and Energy Conservation
关键词 煤柱 综放回收 过空 coal pillar fully mechanized caving recovery passing empty areas
  • 相关文献

参考文献4

  • 1任秉刚.中国综合机械化放顶煤开采[M]北京:煤炭工业出版社,2002.
  • 2侯朝炯;郭励生.煤巷锚杆支护[M]徐州:中国矿业大学出版社,1999.
  • 3吴中立.矿井通风与安全[M]徐州:中国矿业大学出版社,1989.
  • 4钱鸣高;石平五.矿山压力与岩层控制[M]徐州:中国矿业大学出版社,2003.