摘要
叙述了岩巷掘进的五大施工工序以及劳动组织和循环作业组织图表,提出有待改进的关键工艺。
Described five rock roadway excavation construction process as well as the labor organization and cycle operation organization chart, a.nd proposed critical process need to be improved.
出处
《能源与节能》
2012年第12期35-37,共3页
Energy and Energy Conservation
关键词
钻眼爆破
锚杆安装
喷浆工艺
平行作业
滚班制
激光导向仪指示腰线
中深孔光面爆破
drilling and blasting
bolt installation
shotcrete process
parallel operation
Roll shift
instructing waistline with guiding laser
medium-length hole smooth blasting