摘要
着重介绍了武广客运专线清远车站范围DK2105+785~+863左侧滑坡工点病害发生、发展及整治的过程。根据诱发病害的原因及对滑坡体进行稳定分析的结果确定的相应的工程处理措施,使滑坡得到有效控制。
The paper lays the stress on introduction of the causes development, and treatment of landslide disease on the left side of DK2105 + 785~ + 863 section in the scope of Qingyuan Station of Wuhan- Guangzhou PDL. The relevant engineering is thus confirmed according to the causes inducing the disease and the result of stability analysis against the landslide body. It make landsilide control efpectively.
出处
《路基工程》
2012年第6期185-188,191,共5页
Subgrade Engineering
关键词
工程滑坡
病害原因
整治措施
engineering landslide
disease causes