摘要
根据成熟的实践积累,结合某主跨88m连续梁桥挂篮悬臂浇筑施工监控,初步探讨悬浇施工控制计算易发问题,对易发问题和解决问题的方式进行明确,包括墩梁临时刚接模拟,模拟实际施工工况,成桥预拱度计算和设置,预应力参数k,μ参考取值等。根据理论分析与现场实践表明理论值与实测值基本吻合,且主桥自然合龙。
Based on the experience accumulated main-span continuous girder bridge using hangin and combined with the construction monitoring of a 88m g basket cantilever pouring method, this paper discussed the common problems occurred during the control calculation, and proposed solutions for these problems. They include temporary rigid-connection simulation of the piles, simulation of the actual construction conditions, calculation and setting of the bridge pre-arch, reference values for prestressed parameters κ,μ, etc. The theoretical analysis and field practice show that the calculation results matched the site monitoring very well, and the main bridge jointed naturally.
出处
《施工技术》
CAS
北大核心
2012年第12期51-54,共4页
Construction Technology
关键词
桥梁工程
连续梁桥
悬浇施工
监控
仿真
bridges
continuous girder bridges
cantilever-casting construction
monitoring
simulation