摘要
以苏州盾构区间隧道施工为例,深入介绍了盾构机切割桩基技术方案,包括施工方案分析,盾构机选型及改造,广济桥基础预加固处理;盾构机切桩前模拟试验,包括试桩直径及配筋,试桩桩位布置,试桩过程中各项数据监测。详细介绍了通过改造盾构机刀盘和调整掘进参数完成盾构机刀盘直接切割既有跨河桥梁群桩基础实现穿越成功全过程。
Based on construction of shield zone tunnel in Suzhou, the authors introduce technical scheme for the use of shield machine to cut piles, including construction scheme analysis, selection and transformation of shield machine, pre-strengthening of Guangji Bridge foundation. Simulationt test was performed before the cutting, and information including the test pile diameter and reinforcement, testing pile layout, data monitoring during pile testing was introduced. By transforming the cutter head and adjusting parameters of shield driving, the cutter head directly cuts the pile group foundation of existing crossing bridge. This process was introduced in detail.