西宁站改造工程施工组织设计 被引量:3

Design of Construction Organization of Xi’ning Station Reconstruction
下载PDF
导出
摘要 根据西宁站改造工程的主要内容,分析改造工程特点,确定改造工程施工组织。按照"倒排工期、突出重点、科学安排、有序施工"的指导思路,提出西宁站改造施工顺序依次为西宁站既有线运营,维持客车车底取送和机车走行作业现状→建设兰新车场及过渡线路→拨接线路,过渡线路投入运营→建设兰青车场→兰青车场开通,完善兰新车场。根据工程进度计划,给出施工组织的具体步骤。 According to the main contents of Xi'ning reconstruction, the characteristics of the reconstruction engineering are analyzed and the construction organization of the engineering is determined. In accordance with the guidance idea of "reversed arrangement of construction period, emphasizing focal point, scientific arrangement and ordered construction", this paper puts forward the ordinal reconstruction order of Xi'ning Station is existing line operation in Xi'ning Station and keeping operation status of passenger car frame delivery and locomotive running→constructing Lanzhou-Xinjiang Yard and transition linetrack lining and joining and putting transition line into operation→constructing Lanzhou-Xi'ning yard→opening of Lanzhou-Xi'ning yard and improving Lanzhou-Xinjiang Yard. According to the construction schedule, the detailed process of construction organization was provided in the paper.
出处 《铁道运输与经济》 北大核心 2012年第12期38-42,共5页 Railway Transport and Economy
关键词 铁路 改造工程 施工组织 西宁站 Railway Reconstruction Engineering Construction Organization Xi'ning Station
  • 相关文献

参考文献1

  • 1中铁第一勘察设计院集团有限公司.西宁地区铁路西宁站改造及相关工程施工图[R].西安:中铁第一勘察设计院集团有限公司,2012.

同被引文献20

引证文献3

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部