摘要
:因山区铁路建设工程艰巨 ,投资大 ,建设项目立项时 ,必须经多方面论证 ;要使线路方案经济合理 ,需正确选择主要技术标准 ,同时在线路方案研究中 ,应合理确定越岭垭口 ,重视地质选线 ,通过精心设计 ,选出一条经济合理的线路 ,既能满足铁路运输需要 。
Due to the high difficulty in engineering works and big investment of the railway construction in the mountain area,the demonstrations in different aspects should be put forward during setting up the construction projects.The route selection schemes should be economic and reasonable,and the main technical standards should be selected properly.During the research of the route selection schemes,the strip of land between hills should be determined reasonably,and the geological route selection should be taken into attention.Through carefully design,an economic and reasonable route may be selected so as to fulfill not only the requirements of railway transportation,but also to promote the development of the local economy.
出处
《铁道工程学报》
EI
2000年第1期8-12,共5页
Journal of Railway Engineering Society