摘要
锦屏二级水电站3#引水隧洞TBM组装洞,是作为直径12.4m的TBM进行洞内组装面设计施工的、特大断面地下洞室。为克服断面特大、工期紧张等压力,研究了TBM组装洞特大断面分四层共十步的空间交错开挖方法及顺序,确定了适合于上述条件的各层间施工“顶层先行,导洞并举,多层平行,矿体交叉”以及同层“部分前行,余部跟进,支护紧随”的方法和作业顺序。文章简述了特大断面空面交错施工技术在锦屏特大断山TBM组装洞的技术应用。
The design of the No.3 diversion tunnel of the Jinping 11 hydropower station involved the assembly of a TBM with a diameter of 12.4m. The staggered construction consequence, which divided into 4 layers with ten steps to- tal, was adopted because of a large section and tight construction schedule. This method is characterized by advance crown exaction, a simultaneous pilot tunnel, parallel construction, and local advance excavation followed by immedi- ate support. This paper introduces the application of this technique to the construction of the Jingping hydropower sta- tion
出处
《现代隧道技术》
EI
北大核心
2012年第6期139-146,共8页
Modern Tunnelling Technology
关键词
TBM组装洞
特大断面
空间交错
施工技术
TBM assembly cavern
Large section
Staggered space
Construction technique