摘要 介绍了在红海海相珊瑚层和碳酸盐沉积物上的大直径钻孔灌注混凝土后压浆桩的施工过程及桩的载荷试验结果。描述并讨论了在选择场地、钻孔、钢筋、混凝土浇注、以及压浆过程中的施工细节和所遇到的困难,以及场地条件和桩型选择的岩土工程依据。 This work presents the construction procedures and pile load test results of large-diameter bored and grouted cast-in-place concrete piles in coral formations and carbonate sediments in the Red Sea.Construction details and difficulties involved in the process of site preparation,borings,reinforcement,concrete casting,and grouting are described and discussed.Geotechnical engineering considerations that led to the selection of this type of foundation and the conditions of the site are included.
机构地区 中国地质图收馆
出处 《土工基础》 2012年第6期125-127,共3页 Soil Engineering and Foundation
关键词 桩基础 钻孔灌注后压浆桩 海相沉积物 桩基施工法 基桩载荷试验 pile foundations bored and grouted marine sediments construction methodology load testing
  • 相关文献

参考文献7

  • 1Aggarwal S L,Malthorta A K,和Banerjeem R.影响海上结构的长桩设计的钙质土的工程性质[C].美国,休斯顿市.第9届国际海洋技术大会会议录,1977,3:503-512.
  • 2Deshmukh A M,G S K,Rao G V,和Agarwal S L.地质结构对珊瑚岩性能的影响[C].第11届国际土力学与基础工程大会会议录,1985:2397-2400.
  • 3Ghazali F M,Baghdadi Z A,和Mansour O A.红海中桩基在钙质沉积和珊瑚沉积中的对比试验[C].泰国,曼谷.第9届东南亚岩土工程大会会议录,1987.
  • 4Hagnaar J,和Van Den Berg J.在红海中安装海上结构的桩基础[C].第10届国际土力学与基础工程大会会议录,1981:727-730.
  • 5MeClelland B.海上结构的长桩设计[J].美国土木工程师协会,岩土工程学报,1974,100(7):705-747.
  • 6Murff J D.钙质土中的桩基承载力[J].美国土木工程师协会,岩土工程学报,1987,113:490-507.
  • 7Stevenson C A,Thompson C C.在钙质砂和石英砂中的打入式桩基础的性能[C].第7届国际港湾工程大会会议录,1978,1.05/1-1.05/13.