本文介绍在漳州后石电厂取水口工程投标中 ,四航局二公司与四航设计院联合提出替代方案 ,取替原设计方案 ,成为正式施工方案。
During the tendering for the water intake works for Zhangzhou Houshi Power Plant,the Second Company of CHEC-Fourth Navigational Engineering Bureau and Fourth Design Institute of Navigational Engineering jointly made an alternative proposal to substitute for the original design porposal.The alternative proposal was finally accepted and became the formal construction programme.
出处
《中国港湾建设》
2000年第3期49-51,共3页
China Harbour Engineering
关键词
替代方案
工程投标
取水口
优化设计
alternative proposal
Tender
water intake
optimized design