摘要
以一座斜拉桥的换索工程为背景,设计了两种换索方案,分别对两种方案做了换索过程分析。通过将所得到的计算结果进行比较,选择合理的换索方案。
Taking cable - changing project of a cable - stayed bridge as the background, two kinds of cable - changing schemes are designed, and respective analyses of cable - changing processes on two kinds of schemes are made. Through the comparison of obtained calculation results, reasonable cable - changing scheme is selected.
出处
《北方交通》
2012年第12期78-80,共3页
Northern Communications
关键词
斜拉桥
换索
拉索索力
Cable - stayed bridge
Cable - changing
Cable tension