摘要
针对广州小虎岛集输泵站基础下沉的原因进行了分析,探讨了相应处理方案,提出采用单管高压旋喷桩及高压注浆法进行加固形成复合地基,经实践取得了明显的效果。
This paper analyzed the foundation settlement reasons of Guangzhou Tiger Lsland Gathering Station,discussed corresponding treatment scheme,made reinforcement using single pipe high pressure rotary jet grouting pile and high pressure grouting,formed composite foundation,through practice obtained apparent effect.
出处
《山西建筑》
2013年第2期80-82,共3页
Shanxi Architecture
关键词
单管高压旋喷桩
高压注浆桩
袖阀管
single pipe high pressure rotary jet grouting pile
high pressure grouting pile
sleeve valve tube