摘要
以羊角脑隧道为例,介绍了采取地质超前预报、加强监控量测、采用恰当的材料和方法进行封堵以及采取合理的支护和开挖措施等多措并举、多管齐下相结合的综合治理措施,是成功治理隧道突水、突泥灾害的关键。
The Yangjiaonao tunnel as an example, introduced some advanced geological forecast, strengthening the monitoring and measurement, using the appropriate materials and method of sealing and reasonable supporting and excavation measure Duocuobingju, next multibarrel is neat combination o fcomprehensive measures, is the keythat successful management of tunnel water gushing mud disaster.
出处
《工程建设与设计》
2013年第1期118-120,共3页
Construction & Design for Engineering
关键词
隧道
突水
突泥
超前预报
注浆
tunnel
water burst
burst mud
advanced prediction
grouting