钢-混凝土预制板组合梁的组合性能 被引量:3

Experiment of the steel-full depth precast concrete panel beams
原文传递
导出
摘要 通过制作了12个推出试件,研究了栓钉连接件在不同工作环境下的抗剪承载力及其抗滑移性能;并对不同孔型、不同抗剪连接度的3根钢-混凝土预制板组合梁进行了静力性能试验,对比分析了钢-混凝土预制板组合梁的荷载-滑移、荷载-挠度、荷载-组合梁全截面应变及截面整体工作性能.结果表明:预留后灌孔为方孔推出试件的栓钉承载力比圆孔好;孔内填充混凝土强度对栓钉承载力影响很大,孔内混凝土强度高则栓钉承载力好;3根试验梁的截面应变分布满足平截面假定的要求,且均为弯曲破坏形式;组合梁具有良好的组合效应及受弯性能,完全抗剪连接的组合梁与部分抗剪的承载力接近,但完全抗剪组合梁钢梁与混凝土板界面间得滑移值明显小于后者.本文结果将增进对钢-混凝土预制板组合梁的理解和认识,为今后改进该类型梁工程设计提供有价值的参考. Test of twelve push - out specimens under different working conditions to compare and analyze the capacity and the corresponding slip value of the stud shear connector. Meanwhile, tests were also conducted on three composite steel - FDPCP ( Full - Depth Preeast Concrete Panel) beams with different groove and degree of shear connection to investigate the charaeteisties of load -displacement, load -deflection , load -strain of the total cross section and monolithic action of the entire cross section. The results show that, as to the two different kinds of grooves , the strength of the stud shear connectors of square push - out specimens is huger than that of circular specimens with the same condition; the strength of stud shear connectors in steel - concrete composite structure is decided by the strength of concrete surrounding the shear in the holes, with increasing concrete strength, the strength of stud shear connectors improve greatly; the composite steel - FDPCP beams fail in bending, plane section is maintained in composite beams throughout the testing process. The composite steel -FDPCP beams have some merits : good bearing capacity, good anti - bend capability, fast pile - driving pace and perfect work behaviors as a whole ; the ultimate flexural capacity of the composite steel - FDPCP beams with a full shear connection is close to that of a partial shear connection. The outputs of this study are very useful for further understanding of the characteristics of the composite steel - FDPCP beams, it is also expected that the results are valuable for the design of the composite steel - FDPCP beams.
出处 《湖南科技大学学报(自然科学版)》 CAS 北大核心 2012年第4期39-43,共5页 Journal of Hunan University of Science And Technology:Natural Science Edition
基金 湖南省优秀青年骨干教师资金资助(湘教通(2009)391号) 湖南科技大学教改项目资助(J11216)
关键词 钢-混凝土预制板组合梁 推出试件 栓钉 正截面抗弯承载力 力学性能 the composite steel - FDPCP beams push - out specimens studs flexural strength of normalsection mechanical properties
  • 相关文献

参考文献8

二级参考文献53

共引文献242

同被引文献19

  • 1樊健生,聂建国.钢-混凝土组合桥梁研究及应用新进展[J].建筑钢结构进展,2006,8(5):35-39. 被引量:68
  • 2Richard Yen J Y,Lin Y,Lai M T.Composite Beams Subjected to Static and Fatigue Loads[J].Journal of Structural Engineering,1997,123(6):765-771.
  • 3Ahn J H,Kim S H,Jeong Y J.Fatigue Experiment of Stud Welded on Steel Plate for a New Bridge Deck System[J].Steel and Composite Structures,2007,7(5):391-404.
  • 4Lin W W,Yoda T,Taniguchi N.Fatigue Tests on Straight Steel-concrete Composite Beams Subjected to Hogging Moment[J].Journal of Constructional Steel Research,2013,80:42-56.
  • 5Wang Y H,Nie J G,Li J J.Study on Fatigue Property of Steel-concrete Composite Beams and Studs[J].Journal of Constructional Steel Research,2014,94:1-10.
  • 6Lee P G,Shim C S,Chang S P.Static and Fatigue Behavior of Large Stud Shear Connectors for Steel Concrete Composite Bridges[J].Journal of Constructional Steel Research,2005,61:1270-1285.
  • 7Hanswille G,Porsch M,Ustundag C.Resistance of Headed Studs Subjected to Fatigue Loading,Part I:Experimental Study[J].Journal of Constructional Steel Research,2007,63:475-484.
  • 8Hanswille G,Porsch M,Ustundag C.Resistance of Headed Studs Subjected to Fatigue Loading,Part II:Analytical Study[J].Journal of Constructional Steel Research,2007,63:485-493.
  • 9Issa,M A,Yousif A A,Issa M A.Experimental Behavior of Full-depth Precast Concrete Panels for Bridge Rehabilitation[J].ACI Structural Journal,2000,97(3):397-407.
  • 10王宇航,聂建国.基于断裂力学的组合梁栓钉疲劳性能[J].清华大学学报(自然科学版),2009,5(9):1467-1470. 被引量:21