摘要
广西盛隆2×320m2烧结机工程于2012年3月开工建设。出于节能环保的考虑,该工程在总图布置、工艺流程及设备选用等方面采取了一系列措施,设计工序能耗为49.289 3 kg/t,居国内先进水平。
Guangxi Shenglong 2 × 320 m2 sinter machine project was commenced in March of 2012. For the sake of energy saving and environmental protection, a series of measures have been taken in terms of general layout,process flow and equipment selection, the designed process energy consumption is 49. 289 3 kg/t, which is of domestic advanced level.
出处
《烧结球团》
北大核心
2012年第6期33-35,共3页
Sintering and Pelletizing
关键词
烧结机
设计
节能
sinter machine
design
energy saving