期刊文献+

125MW抽汽凝汽式机组改造为背压机组的可行性分析

Feasibility Analysis on Changing 125MW Extraction Condensing Turbine into Back Pressure Steam Turbine
下载PDF
导出
摘要 介绍某电厂125MW抽汽凝汽式汽轮机组概况,提出在基础系统及辅机等不变的前提下将该机组改造为背压机组的思路及要求,阐述汽轮机可采取的改造方案,通过分析改造后机组性能会发生的变化及改造效益,认为将125MW抽汽凝汽式机组改造为背压机组具有可行性。 This paper introduces the 125 MW extraction conden- sing steam turbine,presents the reform thought and principle of changing 125 MW extraction condensing turbine into back-pres- sure steam turbine on the basis of basic system and auxiliary e-- quipment,expounds that reform project, considers that it is the feasibility that 125 MW extraction condensing steam turbine is changed to back-pressure steam turbine through analysis on the characteristic changes and the reformation benefits.
作者 李强华
出处 《河北电力技术》 2012年第6期46-48,共3页 Hebei Electric Power
关键词 抽汽凝汽式机组 背压机组 通流改造 extraction condensing turbine back-pressuresteam turbine flow transformation
  • 相关文献

参考文献1

  • 1DI一5011-1992,电力建设施工及验收技术规范(汽轮机机组篇)[s].

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部