期刊文献+

某曲线连续梁桥的静力荷载试验分析 被引量:7

A static load test for a curve continuous girder bridge
下载PDF
导出
摘要 以重庆市城区某曲线连续梁桥为工程背景,采用有限元计算软件midas/civil建立梁格法有限元模型,进行相关计算。通过结构计算、现场检查、荷载试验等工作,评价该曲线桥梁的工作性能和承载能力,为该桥下一步竣工验收及后期养护提供依据。对今后同类型桥梁的试验测试方法和结构承载能力评价具有一定的参考价值。 It takes a curve continuous girder bridge of Chongqing for the engineering background. The finite element calculation software--Midas/civil is used to establish grillage method finite element model. Through the structure calculation, the field inspection and load test, evaluation is made on the curve bridge working performance and carrying capacity, which will be the basis for the next completion acceptance and later maintenance. The results from the test will be referred to by the similiar bridge engineering.
作者 肖伟 张玉伟
出处 《交通科技与经济》 2013年第1期80-82,共3页 Technology & Economy in Areas of Communications
基金 国家自然科学基金资助项目(50908246)
关键词 曲线桥梁 梁格法 静载试验 curve bridge grillage method static load test
  • 相关文献

参考文献3

  • 1YC-4/1982大跨径混凝土桥梁的试验方法[S].北京:人民交通出版社,1982.
  • 2JTG/T21-2011公路桥梁承载能力检测评定规程[S].北京:人民交通出版社,2011.
  • 3章日凯,王常青.桥梁荷载试验[J].交通标准化,2005,33(12):69-72. 被引量:45

二级参考文献1

共引文献45

同被引文献41

引证文献7

二级引证文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部