摘要 以中国改进型压水堆核电站CPR1000为研究对象,在其蒸汽发生器(SG)二次侧设计了1套非能动排热系统。为验证该系统在主给水管道破裂(MFLB)事故下的热量排出能力,采用RELAP5/MOD3.2程序对系统进行合理的简化并建模。结果表明:MFLB事故发生后,系统内可迅速建立起自然循环流动;该系统的及时投入可使一回路温度和压力的上升得到有效缓解,在隔离受影响的SG之前,一回路未出现整体沸腾,稳压器未满溢,保证了堆芯和一回路冷却剂系统的完整性。 A new secondary passive heat removal system was designed for CPR1000.In order to verify the capability of removing heat for the system under the major feedwater line break(MFLB) accident,the model of the simplified system for CPR1000 was established by using RELAP5/MOD3.2 code.The calculation results show that natural circulation in passive heat removal system is quickly established,and the increasing of temperature and pressure in the primary loop is mitigated due to the timely input of passive heat removal system.There is no bulk boiling in the primary loop and the pressurizer does not overflow before the operator isolates the affected steam generator,which assures the integrity of the core and the main coolant system.
出处 《原子能科学技术》 EI CAS CSCD 北大核心 2012年第12期1434-1439,共6页 Atomic Energy Science and Technology
基金 核能开发项目资助(科工二司[2008]700号)
关键词 CPR1000 非能动排热系统 RELAP5 MOD3 2 主给水管道破裂 CPR1000 passive heat removal system RELAP5/MOD3.2 MFLB
  • 相关文献

参考文献11

  • 1朱继洲,奚树人,单建强,等.核反应堆安全分析[M].西安:西安交通大学出版社,2007.
  • 2肖泽军,卓文彬,陈炳德,白雪松,贾斗南.先进压水堆非能动安全系统研究进展[J].核动力工程,2004,25(1):27-31. 被引量:6
  • 3沈瑾,江光明,唐钢,余红星.先进堆非能动余热排出系统应对全厂断电事故的能力分析[J].核动力工程,2007,28(2):87-90. 被引量:10
  • 4STAO T, KOJIMA Y. Variations of a passive safety containment for a BWR with active and passive safety systems[J]. Nuclear Engineering and Design, 2007, 237(1): 74-86.
  • 5BAEK H, KIM H C, CHANG M H, et al. Safety evaluation of the inherent and passive safe- ty features of the smart design[J]. Annals of Nuclear Energy, 2001, 28(4).. 333-349.
  • 6JUHN P E, KUPITZ J, CLEVELAND J, et al. IAEA activities on passive safety systems and overview of international development[J].Nucle- ar Engineering and Design, 2000, 201(1-2) : 42- 59.
  • 7阎义洲,臧希年.AC600核电站断电事故分析[J].中国电力,2001,34(11):20-23. 被引量:4
  • 8沈瑾,江光明,唐钢.AP1000非能动安全系统初步应用研究[J].国外核动力,2006,27(1):1-6. 被引量:7
  • 9IWAMURA T, MURAO Y, ARAYA F, et al. A concept and safety characteristics of JAERI passive safety reactor (JPSR)[J]. Progress in Nuclear Energy, 1995, 29(Suppl. ) : 397-404.
  • 10SCHAFFRATH A, HICKEN E F, JAEGERS H, et al. Operation conditions of the emergency condenser of the SWR1000 [J].Nuclear Engi- neering and Design, 2005, 235 (10): 1 201- 1 214.

二级参考文献12

共引文献35

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部