摘要
中疏港公路扬水站桥桥台护坡按原设计实施后遭遇风暴潮袭击而毁坏。为确保质量安全,研究应用了“抛石+土工模袋混凝土”护坡,效果良好。
The protection slope of bridge pie damaged by windstorm agitation. In order scheme of "throwing stone + geotextile bag of Yangshuizhan bridge on Zhongshugang road was to ensure quality, the concrete" is adopted, and protection slope rush-repair the effect is very good.
出处
《河北交通职业技术学院学报》
2012年第4期47-49,共3页
Journal of Hebei Jiaotong Vocational and Technical College
关键词
中疏港公路
扬水站桥
风暴潮
毁坏
抢修
方案
Zhongshugang road
Yangshuizhan bridge
windstorm agitation
damage
rush-repair
scheme