摘要
近年来,因变压器强迫油循环方式存在缺陷多、损耗大、维护量大等缺点,逐步被淘汰,冷却系统改造工程逐渐增多。本文通过对一台220千伏变压器冷却方式改造工程的分析,证实了改变变压器冷却方式的可行性,提出了一些施工过程中的经验教训,供大家交流探讨。
In recent years, forced oil circulation for cooling the transformer there is a fault and more ,big loss,maintenance workload and other shortcomings,be phased out,renovation project is gradually increasing.Based on the transformation of a 220kV transformer engineering analysis confirms the feasibility of changing the transformer cooling method, summarizes some lessons learned from the process of transformation, so that we communicate and discuss.
出处
《河南电力》
2012年第1期10-12,共3页
Henan Electric Power
关键词
变压器
冷却系统
改造
transformer
cooling system
transformation