摘要
文献[1]对平顶山第二发电厂4×1000MW机组的4种电气主接线设计方案进行了技术、经济比较后,推荐该工程500kV升压站采用一台半断路器电气主接线方案,但是,启动/备用电源的引接,发电机出口不设置断路器(GCB)等问题有待商榷。
After technique& economy comparison of 4 kinds of main electrical connection design projects for 4×1000MW units of Pingdingshan No.2 power plant, reference introduces main electrical connection project for one and a half breaker for 500kv booster station, however, the problems in leading of start-up/standby power source,generator circuit breaker (GCB) not setting on outlet of generator remain to be discussed.
出处
《河南电力》
2012年第4期25-29,共5页
Henan Electric Power