高应力大断面硐室联合支护技术研究与应用 被引量:1

Technique Research and Application of Combined Support in Large Section Chamber with High Stress
下载PDF
导出
摘要 告成煤矿25采区绞车房是该采区提升运输的心脏,服务年限较长,硐室净断面35.5m2。为确保硐室高质量一次成巷,不变形、不维修,保障巷道长期支护效果,经过研究,制定了一套系统化的支护体系,即采取了分层施工和采用锚网喷+巷壁打锚索+U型钢支架+喷浆+围岩中、深孔注浆支护,先柔后刚的支护形式,较好地解决了大断面硐室支护难题。 With long years of service and net sectional area of chamber being 35.5 m2 , the hoist house of 25 Min- ing Area is the heart of lifting convey in Gaocheng Colliery. To ensure the chamber once--tunneling with high quality, no deformation, no maintenance and long--term support effect , the authors develop a set of support system by layered construction and flexible--rigid--coupling form with wire mesh spray, anchor rope on wall, U-- shaped steel support, shot concrete and surrounding rock grouting, which solves the support problems in large section chamber.
出处 《江西煤炭科技》 2013年第1期77-78,共2页 Jiangxi Coal Science & Technology
关键词 大断面 硐室 联合支护 large section chamber combined support
  • 相关文献

参考文献2

  • 1李大伟.深井与软岩巷道二次支护原理及控制技术[M]北京:煤炭工业出版社,2009.
  • 2钱鸣高;石平五;许家林.矿山压力与岩层控制[M]徐州:中国矿业大学出版社,2010.

同被引文献1

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部