摘要
以贵州毕节机场跑道土基工程为例,针对西南地区山区机场共同特点,分析了山区机场高填方土基沉降规律,详细介绍了高填土沉降试验的监测方法、观测周期、施工情况等内容,根据观测数据得出了科学结论,为该机场后续施工提供了有力依据。
Taking the sub-grade engineering of Guizhou Bijie airport runway as the example, according to the common characteristics of southwest mountainous airport, analyzed the foundation pit settlement rules of mountainous airport high embankment, introduced in detail the monitoring method, observation period, construction situation and other contents of high embankment settlement test, according to the observation data obtained scientific conclusions, provided strong basis for airport subsequent construction.
出处
《山西建筑》
2013年第5期58-60,共3页
Shanxi Architecture
关键词
机场
高填方土基
沉降观测
监测方法
airport, high fill sub-grade, settlement observation, monitoring method