在岭澳核电站二期循环水泵调试期间,发现其存在超功率现象。综合对比了各种处理方案并结合现场的调试进度,优先选择切割叶轮的方法,解决了工程技术问题。
During commissioning of CW pump of Ling'Ao Ⅱ,over-performance was found;.After comprehensive comparison of various treatment options,combined with field commissioning progress,impeller cutting method was preferably chozen to solve the engineering problems.