龙开口水电站坝基深槽施工

Treatment Construction of Deep Trench in Dam Foundation of Longkaikou Hydropower Station
下载PDF
导出
摘要 在龙开口水电站坝基二期开挖时,在溢流坝段发现深槽这一地质缺陷,对坝基稳定影响极大。在对深槽进行处理开挖过程中,通过采用合理的支护手段以及在深槽顶部布置拱形混凝土承载板,最大程度地减少了深槽施工对电站后续工期的影响。 During the stage-II excavation of dam foundation in Longkaikou Hydropower Station, a geological defect with deep trench is exposed in spillway section of dam. The deep trench will lead to serious affects on foundation stability. In the excavation of deep trench for treatment, reasonable supporting is adopted and an arched concrete bearing plate is pouring in trench top as the base of upper concrete construction. This treatment can minimize the impact of deep trench construction on other eonstruetions of power station.
出处 《水力发电》 北大核心 2013年第2期70-71,92,共3页 Water Power
关键词 深槽 开挖 支护 承载板 龙开口水电站 deep trench excavation supporting bearing plate Longkaikou Hydropower Station
  • 相关文献

参考文献3

  • 1张萌.露天矿爆破工程[M]徐州:中国矿业大学出版社,1982.
  • 2庙延钢;王文中.工程爆破与安全[M]昆明:昆明理工大学出版社,2001.
  • 3朱伯芳.大体积混凝土温控应力与温度控制[M]北京:中国电力出版社,1999.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部