摘要
结合广州动车段站场路基施工实践,从施工流程、施工方案、施工方法等方面入手,介绍了吹砂法填筑站场路基的施工工艺,并对质量保证措施及施工应注意事项作了具体说明,指出采用吹砂法填筑站场路基缩短了施工周期,圆满完成了站场路基施工任务。
Combining with the construction practice of Guangzhou train station roadbed,from the construction process,construction schemes,construction methods and other aspects,introduced the construction technology of blowing sand method filling station roadbed,and described in detail the quality assurance measures and construction matters needing attention,pointed out that using blowing sand method filling station roadbed could shorten the construction period,successful completion of station roadbed construction tasks.
出处
《山西建筑》
2013年第4期127-129,共3页
Shanxi Architecture
关键词
吹砂法
站场路基
施工工艺
路堤
blowing sand method
station roadbed
construction technology
roadbed