山岭特长隧道斜井高反坡长距离排水施工技术 被引量:17

On the Long-Distance,High-Reversed-Gradient Draining Construction Techniques for the Inclined Shafts of the Extra-Long Tunnel
下载PDF
导出
摘要 西秦岭特长隧道店子坪一号斜井长1 816m,井口与井底落差220.87m,涌水量大。施工排水采用机械反坡抽排水,利用多级泵站接力将水抽至井外沉淀池,经沉淀后再排放。介绍了斜井排水施工中设计出水量及排水量计算、设备选型、排水系统布置及过程管理,为同类长大隧道工程高反坡、长距离排水施工提供借鉴。 No.1 Inclined Shaft of the extra-long Dianziping Tunnel in the West Qingling Ridges is 1 816 m in length,whose level difference between the pit head and the pit bottom is 220.87 m,and whose yield is great.The construction draining operation is performed by means of the mechanical reversed gradient draining method,with multi-stage pumping stations adopted to relay-drain gush into the subsiding pond outside the pit and then discharge it after subsiding.The calculation and the design of the outletting volume and the inletting volume in the process of the draining construction for the inclined shafts,the arrangement of the draining system,and the management of the construction processes are introduced in the paper,which may serve as a useful reference for similar types of extra-long high reversed gradient,long-distance draining construction operations.
作者 刘艳霞
出处 《国防交通工程与技术》 2013年第1期47-49,55,67,共5页 Traffic Engineering and Technology for National Defence
关键词 特长隧道 斜井 排水 高反坡 长距离 extra-long tunnel inclined shaft drainage high reversed gradient long distance
  • 相关文献

参考文献2

二级参考文献5

  • 1朱大力,1968 襄渝线大巴山隧道现场调查报告,1993年
  • 2李秋枫,铁道工程学报,1988年,1期
  • 3佐腾邦明,トンネルと地下,1983年
  • 4落合敏郎,用水と废水,1972年
  • 5落合敏郎,用水と废水,1968年

共引文献86

同被引文献87

引证文献17

二级引证文献50

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部