介绍面对电网优化运行及自动负荷调度的要求,对原控制系统(电厂侧及中调侧)进行设计修改、施工调试,成功地实现了中调与电厂之间的AGC(自动发电控制)运行方式情况,分析系统的构建、逻辑控制、试验及投运效果。
With the development of China's electric Power,Shajiao C power plant is confronted with more requirements of achieving optimal operation and automatic load dispatching of power network.Through the design modification and construction debugging on the original control system(power plant side and central dispatching side),the automatic generation control(AGC) mode between central dispatching and power plant has been successfully realized.In this paper,the set-up of system, logic control, and testing and commissioning effect are analyzed.
出处
《中国电力》
CSCD
北大核心
2000年第7期73-74,80,共3页
Electric Power
关键词
自发电控制
调度自动化
电网
电厂
automatic generation control (AGC) mode
automatic load regulation (ALR) mode
distributed control system
coordinated control system