盐龙湖取水泵房总规模为60×104m3/d,水源取自水源生态净化湖泊——盐龙湖,泵房建于盐龙湖内,对泵房位置、泵型选择、构筑物形式、进水方式、水泵充水方式等方案进行了论证,确定了可靠的工程方案,缩短了工期,节约了工程投资。目前,该工程已竣工投产,运行状况良好。
The total capacity of Yanlong Lake water intake pumping station is 60×10^4m^3/d. Water is taken from an ecological purification lake, Yanlong Lake, and the pumping station was built inside the lake. The station location, pump type selection, structure form, water pumping way and water filling way were demonstrated. A reliable project scheme was determined, the construction period was shortened, and the project investment was saved. Currently, this project has been completed and put into operation with good effect.
出处
《中国给水排水》
CAS
CSCD
北大核心
2013年第4期50-52,共3页
China Water & Wastewater
关键词
盐龙湖
取水泵房设计
泵房位置
构筑形式
充水方式
water filling Yanlong Lake
water intake pumping station design
station location
structure way