乌东德水电站阴地沟渣场边坡稳定性分析 被引量:9

Stability analysis on side-slope of Yindigou slag field of Wudongde Hydropower Station
下载PDF
导出
摘要 乌东德水电站阴地沟渣场属大型渣场,人工堆渣边坡最高达165 m,且位于水库水位变动区,渣场稳定性对工程施工安全尤为重要。采用Geo-Slope软件对渣场边坡中的控制性结构面进行了稳定性计算和分析,得出了5种不同工况的稳定性分析结果。利用计算结果对渣场边坡的稳定性进行了评价,并提出了防治措施。其成果可供类似工程借鉴。 Yindigou slag field of Wudongde Hydropower Station is of a large scale slag field with the side - slope ot 165 m high and located in the fluctuation zone of reservoir water level, so its stability is very important to construction safety. Through stabili-ty analysis on the control structural plane in the side - slope of slag field by Geo - Slope software, results of 5 different operation conditions are obtained. On the basis of the analysis result, the stability of the side - slope is evaluated and the prevention and control measures are put forward
出处 《人民长江》 北大核心 2013年第3期30-32,共3页 Yangtze River
关键词 渣场边坡 极限平衡法 Geo—Slope软件 稳定性计算 side - slope of slag field limit equilibrium method Geo - Slope software stability analysis
  • 相关文献

同被引文献59

引证文献9

二级引证文献39

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部