22ZK5直线输电铁塔仿真分析

Simulation Analysis of 22ZK5 Straight Line Power Transmission Tower
下载PDF
导出
摘要 以220kV线路猫头直线塔为研究对象,以有限元分析为研究手段,建立桁梁混合模型,对其在不同覆冰载荷作用下的强度、刚度及稳定性(屈曲)问题进行分析。最大位移和最大应力都发生在塔头的挂线点,整体综合位移是从塔头到塔腿逐渐变小。在屈曲分析中,铁塔下曲臂的杆件出现了屈曲,则应加强铁塔塔头的设计。 Take cat head straight line tower of 220kV line as a research object,and finite analysis as an analysis method,a hybrid truss medel has heen etstablished.The strength,rigidity and stability under the action of different icing loads are analyzed.Both maximum displacement and maximun stress occurs at the ligationg terminal of the tower head and the integral displacement from the tower head to tower foot becomes smaller.For the analysis of bucking,the rods of the crank arms under the tower bend,must design a strong tower head.
作者 刘文婧
出处 《电气开关》 2012年第6期75-78,共4页 Electric Switchgear
关键词 直线型猫头铁塔 覆冰 桁梁混合模型 有限元分析 straight cat head tower icing hybrid truss model finite analysis
  • 相关文献

参考文献5

  • 1陈祥和.输电杆塔及基础设计[M]北京:中国电力出版社,20085-25.
  • 2孟遂民;孔伟.架空输电线路设计[M]北京:中国电力出版社,200745-55245-246.
  • 3段进.ANSYS10.0结构分析从入门到精通0结构分析从入门到精通[M].北京:北京科海电子出版社,2006336-337.
  • 4曾程.大跨越输电塔结构极限承载力分析[D]上海:同济大学.
  • 5李永航.输电线路覆冰过大对输电铁塔的强度影响[J].广东建材,2009,32(10):78-79. 被引量:1

二级参考文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部