深厚软土地区高速铁路桥梁沉降规律及修正等代墩基法计算沉降 被引量:6

Study on Settlement Law and Calculation in Revised Equivalent Pier Method of High-speed Railway Bridge in Deep Soft Soil Area
下载PDF
导出
摘要 通过京沪高铁昆山东桥施工及箱梁架设期间墩身沉降观测,分析了深厚软土地区高速铁路桥梁工后沉降规律.得出墩顶荷载和基础沉降量的最大值发生在架梁作业时,架梁结束后基础沉降有小幅反弹,架梁后3个月内基础沉降均已收敛达到无砟轨道铺设条件.采用修正的等代墩基法理论计算方法对深厚软土地区桥梁沉降进行计算,并分析计算值和实测值存在差异的原因,得出土体压缩模量、施工工艺及观测时间对基础沉降有较大影响等结论. In this paper, the general rule of the high-speed railway bridge settlement after construction was analyzed through field measurements in deep soft soil area on Beijing--Shanghai high-speed rail- way Kunshan eastern bridge. And some conclusions were drawn. The maximum of the load on the pier and the settlement of the bridge appear when the beam is erecting. The settlement of cap slightly
出处 《武汉理工大学学报(交通科学与工程版)》 2013年第1期6-10,共5页 Journal of Wuhan University of Technology(Transportation Science & Engineering)
基金 国家自然科学基金资助项目(批准号:50808177 50708033) 湖南省科技厅重点支持项目(批准号:04SK2008)资助
关键词 高速铁路 桥梁工程 深厚软土 沉降观测 修正等代墩基 high-speed railway bridge engineering deep soft soil settlement observation revised e-quivalent pier
  • 相关文献

参考文献13

二级参考文献119

共引文献278

同被引文献13

引证文献6

二级引证文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部