摘要
详细介绍了海外项目广泛采用的PILLARD重油系统的安装和调试过程。其中对重油罐的制作安装、重油系统设备安装、窑头窑尾燃烧器安装、管道系统安装试压进行了逐一介绍;在此基础上,对重油系统的运行调试、点火操作、技术细节及需要注意的问题等着重进行了分析和强调。
Installation and adjustment of PILARD heavy oil burner used wide in oversea project were introduced in detail as well as the installation of heavy oil tank,heavy oil system equipment,burner at kiln ends and pipe network one by one. On that base,the running adjustment, ignition operation,teehnial detail and cautions were analysed and laid stress on.
出处
《水泥工程》
CAS
2013年第1期44-46,共3页
Cement Engineering