水电工程人工砂石生产的成组作业排序研究 被引量:5

Study on Artificial Aggregate Production Group Scheduling of Hydropower Project
下载PDF
导出
摘要 针对水电工程人工砂石生产线容易出现无序化导致生产进度滞后和成本增加的问题,考虑人工砂石生产线的特点对人工砂石生产作业进行优化排序,根据不同人工砂石在加工上的相似性,在满足约束条件的情况下以总加工流程时间最小化为目标函数,建立了砂石生产线的成组作业排序模型,并利用CDS启发式算法进行求解,达到人工砂石生产系统最优化的目标。通过工程实例验证了该模型及算法的合理性。 Disorderliness of artificial aggregate production line is easy to emerge in hydropower project,which can result in production schedule delays and cost issues.Owing to this problem and taking into account the characteristics of artificial aggregate production line,it is import to optimize the sorting of artificial aggregate production processes.According to the similarity of different artificial aggregate processing and meeting constraints,taking minimization total process time as objective function,group scheduling model of aggregate production line is established.By using CDS heuristic algorithm,the goal of artificial aggregate production system optimization is achieved.Rationality of the model and algorithm is verified by an engineering example.
出处 《水电能源科学》 北大核心 2013年第2期154-156,共3页 Water Resources and Power
基金 三峡大学研究生科研创新基金资助项目(2011CX002) 三峡大学人才启动基金资助项目(KJ2009B068)
关键词 水电工程 砂石生产线 成组作业排序 CDS启发式算法 系统优化 hydropower project aggregate production line group scheduling CDS heuristic algorithm system optimization
  • 相关文献

参考文献4

二级参考文献17

  • 1胡志根,肖焕雄.砂石料料场开采顺序优化模型研究[J].水利水电技术,1993,24(10):35-38. 被引量:2
  • 2胡志根,肖焕雄.施工系统中混凝土拌和工厂位置选择综合评价模型[J].水利学报,1994,26(3):26-32. 被引量:3
  • 3Wooldridge M.An introduction to multiagent systems[M].[s.L.]:John Wiley&Sons Inc Press,2002:3-30.
  • 4Date R A,Chow J H.A Reliable Coordinated Decentralized Control System Design[J].Proc.of the 28th CDC,1989:1295-1300.
  • 5Davison E J,Wang S H.Properties of Linear Time-invariant Multivariable Systems Subject to Arbitrary Output and State Feedback[J].IEEE Trans.AC,1973,18(1):24-32.
  • 6Mitchell T M.Machine learning[M].[s.L.]:McGraw Hill Press,1997:263-276.
  • 7Candler W,Townsely R.A linear two-level programming problem[J].Computers and Operations Reseaech,1982,(9):59-76.
  • 8Bialas W F,Karwan M H.Two_level linear programming[J].Management Science,1984,30:1004-1020.
  • 9Bard J F,Falk J E.An explicit solution to the multi-level programming problem[J].Computers and Operations Research,1982,(9):77-100.
  • 10Bard J F,Moore J T.A branch and bound algorithm for the bi-level programming problem[J].SIAM Journal of Scientific and Statistical Computing,1990,(18):35-42.

共引文献9

同被引文献29

引证文献5

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部