结合工程实例系统地论述了1 000 kV变电站屋外架构基础地脚螺栓及GIS基础预埋件预埋精度的作业方法以及主要的质量控制措施,为今后类似有高精度要求的大型埋件工程安装作业施工应用标准工艺措施方面提供了切实可行的具体作业方法。
Combining with the engineering examples, the paper has the systematic indication of the outdoor framework anchor bolt of 1 000 kV substation, the operation methods for the embedded accuracy of the GIS foundation built-in fitting and the main quality control measures, and provides some feasible operation methods for the adoption of the standard craft measures of the construction and installation of the large embedded fitting with similar accuracy.
出处
《山西建筑》
2013年第7期99-101,共3页
Shanxi Architecture
关键词
屋外架构地脚螺栓预埋精度
架构锚固板
GIS基础预埋件微调装置
embedded accuracy of outdoor framework anchor bolt
framework anchor plate
micromatic setting of GIS foundation built-in fitting