摘要
介绍了在国道307线张家河至杨家峪段公路改建工程K8+345~K8+675高填方路段施工与质量控制,采用强夯后增加了填土密实度,有效防止了路基的不均匀沉降,真正做到了路基稳定,有效防止了因路基不均匀沉降而引发的路基病害。
The paper introduces the construction and quality control of the highly-filled section from K8 + 345 to K8 + 675 of the reconstruction projects from Zhangjiahe to Yangjiayu along 307 National Road, indicates the compaction of the filled soil is improved after the dynamic consolidation, so as to prevent the uneven settlement of the roadbeds efficiently, ensure the roadbed stability, and avoid those roadbed diseases caused by the uneven settlement of roadbeds.
出处
《山西建筑》
2013年第7期159-160,共2页
Shanxi Architecture
关键词
公路改建
强夯
高填路基
质量控制
road reconstruction
dynamic consolidation
highly-filled roadbed
quality control