某大型钢厂端部拔柱吊车梁系统设计

THE DESIGN OF CRANE BEAM SYSTEM WITH COLUMN REMOVED IN A LARGE STEEL FACTORY
原文传递
导出
摘要 针对某大型线棒材车间角部柱子拔除后形成的大悬臂吊车梁系统,采用屋盖肢桁架承受屋面荷载、连续悬臂吊车梁传递吊车荷载的结构形式。同时设计中通过节点细部构造,保证厂房系统的空间整体性及构件间变形协调。 The large cantilever crane girder system was formed after removing the corner column in a large wire bar workshop.The load of roof was carried by the roof limb truss and the load of crane was carried by the continuous cantilever crane beam.At the same time,through the design of detail treatment,the system spatial entirety and structural deformation coordination were ensured.
出处 《工业建筑》 CSCD 北大核心 2013年第2期134-137,共4页 Industrial Construction
关键词 钢吊车梁 连续吊车梁 大悬臂 拔柱 steel crane beam continuous crane beam large cantilever column-removing
  • 相关文献

参考文献5

  • 1崔佳;魏明钟;赵熙元.钢结构设计规范理解与应用[M]北京:中国建筑工业出版社,2004346.
  • 2刘昌杞;张利群;付丰博.国外桥式吊车分级和荷载规定的动向[J]工业建筑,1988(11):12-129.
  • 3张利群,付丰博.大型吊车梁的制作[J].工业建筑,2005,35(z1):783-784. 被引量:1
  • 4薄占秀.冶金工业厂房设计的若干问题[J].工业建筑,1993,23(8):19-25. 被引量:1
  • 5朱国华.钢吊车梁系统空间作用的分析和计算(上)[J]工业建筑,1980(04):48-52.