摘要
老挝南立1—2水电站泄洪(兼导流)洞压力洞段砼衬砌应用Ф12m弯、直段全圆液压钢模台车施工获得成功。本文介绍该台车和施工特点,可供同类工程借鉴。
The application of whole-circle hydrauhc steel form jumbo ot curvmg & stralgnt secnon with a olameter of 12m in concrete construction of spillway and diversion tunnel for Nani 1-2 Project in Laos obtains the success; this paper will give an introduction about this jumbo and construction features, which can also be as a reference for the similar projects.
关键词
老挝南立1—2水电站
泄洪(兼导流)洞
弯
直段钢模台车施工应用
Nani 1-2 hydropower station in Laos, spillway and diversion tunnel, whole-circle hydraulic steel form jumbo of curving & straight section with a diameter of 12m